What are the rules for placing concrete in cold weather on Illinois DOT projects?
Concrete must be protected when air temps drop below 45°F (7°C) or during Dec 1–Mar 15. Protection (insulation with R-values per pour thickness/temp or heated enclosures) must be approved by the Engineer and kept in place until concrete is 7 days old (96 hrs for approach slabs). Concrete temps must stay ≥40°F (4°C) for 48 hrs post-placement, with gradual cooling if temp differential exceeds 35°F (19°C). Placement stops when air temps fall to 40°F (4°C) or below (35°F/2°C for non-structural concrete) unless approved. Pre-placement materials/equipment must be approved, and a cold weather plan (e.g., heated materials) is required if temps <17°F (-8°C) [1,3,5].
Every answer carries its source — tap a citation to read the official document.
This answer came from Verika — an expert in your pocket. Ask anything, out loud or typed; answers come from your region’s regulations and your team’s own knowledge, cited to the source. If it isn’t in the sources, Verika says so.
Verika provides information with citations to help you find and understand the rules that apply to your work. It is not a substitute for professional engineering or legal judgment. Answer generated 2026-08-28; always confirm against the cited source for your project.