What are the rules for placing concrete in cold weather on North Dakota DOT projects?

Submit a cold weather protection plan if National Weather Service forecasts air temps below 40°F during curing; maintain concrete surface temp between 40°F–90°F for 5 consecutive days using admixtures, heated components, insulation/enclosures, and monitored temps; avoid sudden temp changes; reduce enclosure temp to ambient at ≤15°F/hour before removal; Engineer approval required before placement [1,3,5,7].

Every answer carries its source — tap a citation to read the official document.

This answer came from Verika — an expert in your pocket. Ask anything, out loud or typed; answers come from your region’s regulations and your team’s own knowledge, cited to the source. If it isn’t in the sources, Verika says so.

Verika provides information with citations to help you find and understand the rules that apply to your work. It is not a substitute for professional engineering or legal judgment. Answer generated 2026-08-28; always confirm against the cited source for your project.

More North Dakota answers