What are the rules for placing concrete in cold weather on Oregon DOT projects?
Do not place concrete if air temp is below 40°F on placement day or forecasted for 7 days (14 for decks) unless an approved Cold Weather Plan is submitted. The plan must ensure concrete temp stays ≥50°F using methods like heated enclosures or insulated forms, and maintain ≥60°F concrete placement temp. Keep forms, reinforcement, and foundations frost-free. Use heated water (≥70°F, ≤150°F) or aggregates (≤80°F concrete temp) if needed. Monitor with 24-hour thermometers. For bridge decks, ensure no precipitation is forecast within 2 hours before/after placement and evaporation rate <0.10 lb/sq ft/hr [1].
Every answer carries its source — tap a citation to read the official document.
This answer came from Verika — an expert in your pocket. Ask anything, out loud or typed; answers come from your region’s regulations and your team’s own knowledge, cited to the source. If it isn’t in the sources, Verika says so.
Verika provides information with citations to help you find and understand the rules that apply to your work. It is not a substitute for professional engineering or legal judgment. Answer generated 2026-08-28; always confirm against the cited source for your project.