What are the rules for placing concrete in cold weather on Washington DOT projects?
Concrete must be maintained at ≥40°F for the first 7 days and ≥35°F thereafter during the Cold Weather Protection Period (7 days or cure duration, whichever is longer). Submit a Type 2 Working Drawing with a cold weather concreting procedure before placement. Install temperature sensors (1 per 100 yd³) 1.5" from concrete face and on surfaces; record temps hourly. If temps fall below 40°F in the first 7 days, no curing time is awarded and the period extends 1 day. If temps fall below 35°F, concrete may be rejected. Extra protection is required for exposed surfaces, corners, edges, thin sections, and steel forms. Review 7-day temperature predictions from NOAA before placement.
Every answer carries its source — tap a citation to read the official document.
This answer came from Verika — an expert in your pocket. Ask anything, out loud or typed; answers come from your region’s regulations and your team’s own knowledge, cited to the source. If it isn’t in the sources, Verika says so.
Verika provides information with citations to help you find and understand the rules that apply to your work. It is not a substitute for professional engineering or legal judgment. Answer generated 2026-08-28; always confirm against the cited source for your project.